Designers: step-by-step guide to plumbing and drainlaying self-certification
Last updated: 7 September 2026
This guide provides step-by-step instructions to use the self-certification for plumbing and drainlaying scheme. It clarifies roles and responsibilities for designers and explains important steps and considerations.
Step 1: Designer determines whether self-certification may be suitable
The designer will discuss the project with the owner and project team.
Together they will consider whether the proposed plumbing and drainlaying will qualify for self-certification and whether to use this pathway.
Step 2: The work is designed
The designer prepares plans and specifications that:
- comply with the Building Code
- clearly identify the proposed self-certifiable plumbing and drainlaying and what will instead go through the building consent authority (BCA) inspection process
- specify applicable compliance pathways – only plumbing and drainlaying designed to an Acceptable Solution or Verification Method is eligible, unless it’s a qualifying on-site system.
The designer should clearly show which work will be self-certified and which work will be inspected by a BCA.
Step 3: Designer coordinates with practitioners
The designer will work with:
- endorsed plumbers
- endorsed drainlayers
- engineers
- other designers
to ensure the proposed scope of self-certification is understood.
Step 4: Designer supports the building consent application
In the building consent application, the designer must:
- describe the work proposed to be self-certified and how it’s intended to be carried out (whether the endorsed plumber or drainlayer will carry out, assist with, or supervise the plumbing and drainlaying)
- provide the name of the endorsed plumber or drainlayer, if known
- provide plans and specifications that will meet the requirements of the Building Code.
Step 5: Designer responds to requests for information
If requested by the BCA, the designer should:
- clarify design details
- provide additional information, whether it’s about proposed self-certified work or otherwise
- explain proposed compliance pathways.
Step 6: Design changes are managed
If changes occur during construction, the designer:
- assesses whether consented drawings need updating
- supports minor variations or building consent amendment applications where required.
Step 7: Designer updates documentation
Where changes are approved, the designer:
- revises plans and specifications
- clearly identifies any changes affecting self-certification.
Self-certification is optional. If plumbing and drainlaying work does not require a building consent, it is not eligible for the scheme. This is because self-certification removes the need for BCA inspections for eligible work listed on the building consent as self-certifiable.