1000 Determinations match your query
Show detailed results

2019/013: Regarding the refusal to issue a code compliance certificate for the relocation of and 18-year-old alterations to a house

This determination considers the compliance of consented work for the relocation of an existing building onto a new site and alterations to the building.  The authority refused to issue the code compliance certificate for the work because of concerns over the performance of a membrane roof to a new extension built as part of the relocation consent. 

About this document

2018/051: Refusal to issue a code compliance certificate for a 9-year-old house with mixed claddings

This determination considers the compliance of a consented building where there was delay in completing the consented work.  The determination considers the authority’s reasons for declining to issue the code compliance certificate for the work; the authority’s reasons were principally concerned with the building’s compliance with Building Code Clause E2 — External moisture.

About this document

2018/046: Refusal to issue a code compliance certificate for alterations to a 16-year-old building

This determination considers the compliance of consented alterations carried out on an existing building for which an earlier code compliance certificate also had not been issued and where a significant portion of the existing building remained unaltered. The determination considers the authority’s reasons for declining the code compliance certificate for the work, and the provisions of section 115 (change of use) in relation to the work.

About this document

2018/040: Refusal to issue a building consent in respect of custom window joinery

This determination considers whether the authority correctly exercised its powers in refusing to issue a building consent for a new house with a fixed glazing system.

About this document

2018/034: Refusal of a code compliance certificate for an addition

This determination considers the authority's refusal to issue the code compliance certificate for a substantial addition to an existing studio building. The refusal arose from matters related to Building Code Clauses D1, E2, E3, and F4, but the principle issue was an ongoing dispute about the water from neighbouring properties and a small drain that has been installed to divert some of this water. The determination considers whether the drain formed part of the consented work or not.

About this document

2018/029: Refusal to issue a code compliance certificate for a 14-year-old house with mixed claddings

This determination considers the compliance of a 14-year-old building. The determination considers the authority’s reasons for refusing to issue the code compliance certificate and whether the building work complies with the requirements of the Building Code.

About this document

2018/021: Refusal to issue a building consent for a house with membrane roof

This determination considers the compliance of low-pitched membrane roofs to a proposed three storey house.  The roofs are inward-sloping and employ slopes less than provided for in the Acceptable Solution for Clause E2 External moisture.

About this document

2018/019: Compliance of the base of a wall to a large shed containing a dwelling

This determination considers the compliance of a base flashing detail installed to a portion of a shed containing a dwelling to resolve moisture ingress.  The determination discusses the extent of the remedial work required in relation to the uses of the shed and their relative Building Code obligations.

About this document

2018/012: Refusal to issue two code compliance certificates for alterations and additions to a house

This determination considers the compliance of alteration and additions to an existing two-storey house that was the subject of two building consents.  The determination considers the compliance of the as-built work and whether the authority was correct in declining to issue code compliance certificates for the work.

About this document

2018/009: Refusal to issue a code compliance certificate in respect of remedial work to decks

This determination considers the compliance of the remedial work carried out to eight decks. The determination considers the authority’s reasons for refusing to issue the code compliance certificate and whether the building work complies with the requirements of the Building Code.

About this document

This information is published by the Ministry of Business, Innovation and Employment’s Chief Executive. It is a general guide only and, if used, does not relieve any person of the obligation to consider any matter to which the information relates according to the circumstances of the particular case. Expert advice may be required in specific circumstances. Where this information relates to assisting people: