Quiz answers: Doing it right with jack and pack

 

Doing it right with jack and pack

1) How far out of plumb would a pile need to be before you should replace it?

b. 15 mm

2) I want to pack only one pile in my repair, how much can I pack it without needing to replace it?

c. 100 mm

3) What does Schedule 1 of the Building Act tell you?

c. What building work does not require a building consent

4) Where can I get more information about repairing and relevelling foundations?

d. All of the above

This information is published by the Ministry of Business, Innovation and Employment’s Chief Executive. It is a general guide only and, if used, does not relieve any person of the obligation to consider any matter to which the information relates according to the circumstances of the particular case. Expert advice may be required in specific circumstances. Where this information relates to assisting people: