Stages of the building process

Last updated: 19 December 2023

Stages of the building process

Every building project is different, but you still need to tick off essential stages to make it a success. Understand the stages of a building project so you know what you need to do and build it right.

Your building project might be quick and simple or complex. It might be an alteration, a renovation or a completely new build. It could be a seaside holiday house or a multi-unit central city apartment building.

The size and complexity of the finished build can affect the duration and complexity of the process. Whatever you're planning, you should generally follow these stages:

1 – Planning a successful build

Get your ideas together, separating out what you must achieve and would like to achieve, so that you can think about priorities, budget and timing. You can get some idea of cost from designers or builders, so that you know whether it’s a realistic project.

The location of your land, and the position of your building site on it, can have a big impact on your project.

You need to think about the finished building and how it needs to sit in relation to:

  • sun
  • wind
  • water, electricity and other services
  • boundaries (a registered surveyor can remove uncertainty)
  • neighbours (preserve your privacy and theirs)
  • access onto and around the site (for example, paths, driveways and door placement)
  • any hills or slopes (and how they might affect your finished height and width)
  • existing features that you want to retain (for example, trees or outbuildings).

If you're planning a rural build, there might be other things to think about. For example, do you need a septic tank? Will you have to store your own emergency water supply for putting out fires?

You might be surprised to know that some renovation projects can be more complicated than a new build.

Talk to your council to get a better understanding of your land, how your ideas will fit and whether you'll need a building consent, resource consent or any other permits.

The council can also produce a project information memorandum (PIM), a report specific to your project that can make planning and design easier and more accurate.

As your ideas come together, think again about what you can afford and how you will pay for it.

When you're choosing people to do the work, you need to think about:

  • how involved you will be (realistically, this depends on your skills, energy and other commitments. There are advantages and disadvantages in doing the work yourself. It might seem cheaper but you need to know what you are doing and your work must still comply with the Building Code.)
  • who you have in mind (architect, builder or a combination) and:
    • whether they're available
    • whether they usually work with another building professional
    • if you're putting them together, will they work well together?
  • any legal restrictions on who can do the work (for example, if there is restricted building work)
  • who will project manage the work.

Scope your project has more details.

Understand your land includes some things you might need to consider.

Renovations differ to new builds highlights some of the differences.

Get the right person outlines why you might need specialists.

You don’t have to decide everything at this stage, but the more you find out early on, the better informed you and your plans will be.

Get your design right

Brief your designer well, telling them what you want and how much you have to spend. Agree on concept drawings.

Once you have the full design, go through it in great detail. Try to consider it from every angle, time of day and stage of life including:

  • how you will use the space
  • what it will look like
  • whether there will be enough light inside
  • what building materials you'll use.

Your plans form the basis of your building consent application, if you need one. You can change them after building consent has been issued, by talking to your council, but there will be time delays and could be additional costs. This applied to every part of the plan, including the materials specified. Any variation from the consented plans could also affect progress, increase cost and delay final sign-off.  

Check if you need consents

Get the right people for your project

If you’re going to manage the project, be aware of your responsibilities. If you’re not the project manager, you still have overall responsibility for making sure everything in the building consent happens.

Confirm who the project manager is in your design and building contracts (it could be your architect, designer, builder or a professional project manager).

It’s often part of the project manager’s role to arrange the builder and tradespeople. Work out if that’s how you will do it, and include this in any contract. You can also hire a quantity surveyor to confirm how much of each material is needed, and provide a cost estimate based on your plans.

Approach a shortlist of builders and ask for detailed quotes (not estimates), based on the project plans and/or the quantity surveyor’s report. Make sure they can work within your timeframe.

When comparing quotes, ensure they include the same scope of building work, materials, fixtures and finish so that you can accurately compare them.

Follow the same process to engage subcontractors if you are hiring them. Subcontractors often contract directly to the main contractor.

Contracts

Formalise all roles in legal contracts, spelling out what you mean so that all parties have a clear understanding.

Get a written contract with your builder, including details of guarantees, payment schedules and completion dates. They will probably provide a contract, but you can ask for changes or even provide your own. Whichever you choose, make sure it covers everyone's needs and involve your lawyer.

Make sure you have the funds to pay for the project before the work begins and understand the payment terms agreed with the building contractor.

As the project progresses, think carefully before agreeing to pay more than the agreed cost of any work that has been completed or the agreed cost of any materials that have been supplied when you make any payments.

Insurance

Find out how to protect yourself during the project by talking to your insurer and possibly your bank.

Your insurer may want information about your contractors' insurance and indemnities during a build.

If you have a mortgage on your property, your bank may require you to keep them informed of significant changes to your property.

If you are using a designer or architect, they should have professional indemnity insurance, to ensure they can pay for repairs if any problems occur as a result of their design.

Plan for health and safety

Have a health and safety plan in place from day one of construction, and make sure everyone keeps to it. Understand your obligations under the Health and Safety at Work Act.

Health and safety on site should be a priority.

2 – Get a building consent

Review your plans and budget

You’re about to apply for building consent, so review your plans and budget. This is the time to decide whether you need to make any changes. If you want to make variations later, you will need to apply to amend the consent, pay a fee and potentially delay your project.

Apply for a building consent and any other consents or permits

Make sure the person completing the application knows what to do and how to make a good application. It has to include all of the requested information, including detailed drawings and evidence of compliance with the Building Code.

If you have restricted building work, you need to name your licensed building practitioner in the building consent application or as soon as you appoint someone.

If you require resource consent or any other permits, apply for them as well.

If you haven't already got a PIM, you can order one at the same time as you apply for building consent (although it will probably help your planning if you get it earlier).

Think about your timing. Your building consent will lapse if you don’t start the building work within 12 months, unless you have arranged an extension with your council. So give yourself and your building team enough time to complete the project.

Apply for building consent

3 - Build to the consent

Begin construction

Once you have building consent, construction can begin. As soon as you know the start date, you need to tell your council. This date is important as you need to start your project within 12 months of receiving your building consent and finish it within two years. It might seem a long way off, but the date will be used in the council's final project sign-off, and is part of the information you need to gather throughout the project.

You or your project manager, builder or architect need to monitor progress and keep the council informed. Organise inspections and ensure they happen.

If your work is not progressing as planned, that's another reason to talk to your council. They can help you identify and document variations or amendments to your building consent.

Pay bills as milestones are met or as you've agreed in your contracts.

Collect energy work certificates for electrical and gas work as it is finished. Keep them on site with your other papers, as your council will want to see them before they sign-off your code compliance certificate (CCC).

Building to the consent

4 – Sign-off and maintain your property

Complete your project

Ensure everything has been done as set out in your building consent, plans and contracts. You need to let your builder know of any problems within 12 months of the end of the build.

You also need to make all final payments, as agreed in your contracts. Ensure all council fees have been paid as well, so that you can get council sign-off in the form of a code compliance certificate (CCC).

If more inspections were required or they took longer than originally anticipated, there may be additional fees. These may not be calculated until after your final inspection, but will need to be paid before your code compliance certificate is issued.

Apply to your council for your code compliance certificate (CCC). The council may need a few days’ notice to review your project before they make their final inspection.

Maintenance protects your investment

Your contractors need to let you know about any required maintenance related to products or materials. You'll need to keep to the instructions so that any warranties and guarantees are effective.

For most domestic building projects, the code compliance certificate (CCC) is the end of the inspection process. However, if your house has a specified system, such as a cable car, it will need regular, ongoing monitoring for safety reasons.

Sign off and maintenance

How helpful was this information?

How helpful was this information?

Please note your feedback is anonymous. If you need a response, contact us.

This information is published by the Ministry of Business, Innovation and Employment’s Chief Executive. It is a general guide only and, if used, does not relieve any person of the obligation to consider any matter to which the information relates according to the circumstances of the particular case. Expert advice may be required in specific circumstances. Where this information relates to assisting people: